CRP SCHEDULE HOMESpecial Projects Statewide

Project
Group Status Target Complete Contact Segment
Completed 1911
A Water and Nutrient Budget for Caddo Lake CRP Submitted for Approval 8/31/2007 Jennifer Delk 0401, 0402, 0407, 0409
Agricultural NPS Remediation in the Cedar Creek Reservoir Watershed TSSWCB In Progress 9/30/2010 Lee Munz 0818
Alligator Bayou Aquatic Life Assessment (ALA) SWQM Completed 8/31/2005 Bill Harrison 0702A
Aquatic Life Assessment (ALA) for Dixon Creek. SWQM Completed 10/15/2003 Bill Harrison 0101A
Aquatic Life Assessment (ALA) of Little Pine Island Bayou. SWQM Sampling 10/15/2008 Bill Harrison 0607B
Aquatic Life Assessment (ALA) of White Oak Creek. SWQM Completed 10/15/2002 Michele Blair 0303B
Aquilla - Atrazine TMDL Completed Arthur Talley 1254
Aquilla - Atrazine - Implementation Plan TMDL Completed Arthur Talley 1254
Archer/Jack Counties Saltwater Minimization NPS Completed 8/31/2006 Sherri Serna 0202, 0211, 0812
Armand Bayou - DO TMDL Completed Larry Koenig 1113, 1113A
Armand Bayou Above Tidal - Bacteria TMDL In Progress 8/30/2009 Roger Miranda 1113A
Armand Bayou Continuous Water Quality Monitoring (CWQM) Project SWQM Sampling 8/31/2009 Christine Kolbe 1113
Armand Bayou DO Evaluation WQS Completed 12/21/2004 Robert Burgess 1113, 1113A
Arroyo Colorado - Bacteria TMDL In Progress 2/2/2009 Jason Leifester 2202
Arroyo Colorado - Legacy TMDL Completed Roger Miranda 2202, 2202A
Arroyo Colorado - Legacy - Fish Tissue Sampling TMDL Completed 8/31/2007 Dania Grundmann 2002
Arroyo Colorado - Legacy - Implementation Plan TMDL Completed Roger Miranda 2202, 2202A
Arroyo Colorado - Organics TMDL Completed Roger Miranda 2202
Arroyo Colorado - Organics - Implementation Plan TMDL Planning 4/26/2010 Roger Miranda 2202
Arroyo Colorado Agricultural Nonpoint Source Assessment TSSWCB Sampling 9/30/2009 Pamela Casebolt 2201
Arroyo Colorado Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 10/1/2009 Anne Rogers 2201
Arroyo Colorado -DO Sampling & Remodeling TMDL In Progress 5/26/2010 Roger Miranda 2201
Arroyo Colorado Tidal - DO TMDL Completed Roger Miranda 2201
Arroyo Colorado Watershed Protection Plan TMDL Completed Roger Miranda 2201
Assessing Water Quality Management Plan Implementation in the Middle and South Bosque River and Hog Creek Watersheds TSSWCB Planning 9/30/2010 Loren Henley 1225, 1246, 1246D, 1246E
Assessment and Mitigation of Agricultural and Other NPS Activities in the Cypress Creek Basin TSSWCB In Progress 6/30/2009 Mitch Conine 0403, 0404
Assessment and targeting of Bacterial Sources in the South Nolan Creek Watershed NPS Report Preparation 8/31/2008 Anju Chalise 1218
Assessment of NPS Contributions from the City of Killeen Urbanized Area in the Lampasas Watershed NPS Sampling 8/31/2009 Anju Chalise 1217
Assessment of NPS Pollution from Cropland in the Oso Bay Watershed TSSWCB Report Preparation 9/30/2010 Mitch Conine 2485A
Assessment of Springtime Contributions of Nutrients and Bacteria to the NBR TSSWCB Sampling 8/31/2008 Loren Henley 1255
Atascosa River - Bacteria TMDL Sampling 7/27/2009 Andrew Sullivan 2107
Athletic Field Topdressing as a Commercial Market for Compost from Dairy Manure TSSWCB Report Preparation 4/30/2008 Loren Henley 1255
Barton Creek/Barton Springs Sediment Toxicity Study SWQM In Progress 8/31/2008 Robin Cypher 0602, 1430, 1430A
Bastrop Bayou Watershed Protection Plan and Implementation of NPS Best Management Practices NPS In Progress 8/31/2009 Bill Carter 1105
Beals Creek and Colorado River above E.V. Spence Reservoir Cont. Water Quality Mon. (CWQM) Project. SWQM Sampling Robin Cypher 1411, 1412, 1412B
Biological Assessment of Harris Creek SWQM Completed 9/30/2002 Brenda Archer 0506A
Black Bayou UAA WQS Submitted for Approval 11/30/2006 Gregg Easley 0406
Black Cypress Bayou - Biological, Physical, and Chemical Survey WQS Submitted for Approval Gregg Easley 0402A
BMP verification using observed water quality data and watershed planning for implementation of BMPs TSSWCB In Progress 7/1/2008 Pamela Casebolt 0814, 0836
Booger Branch Use Attainability Analysis WQS Sampling Gregg Easley 0602A
Bosque and Leon Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling Jill Csekitz 1221A, 1226, 1226B, 1255, 1255C
Brady Creek NPS Abatement Demonstration Project, Watershed Characterization NPS Sampling 8/31/2008 Lauren Bilbe 1416
Brandy Branch Reservoir - Selenium in Fish TMDL Completed Dania Grundmann 0505E
Brays Bayou - Bacteria TMDL Report Preparation 5/11/2009 Ron Stein 1007B, 1007C, 1007E, 1007L, 1007P
Broad-based Communication and Forecasting for Environmental Quality TSSWCB In Progress 9/30/2010 Loren Henley 0901, 0902, 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1013, 1014, 1016, 1017, 1101, 1102, 1103, 1104, 1108, 1110, 1111, 1113, 1202, 1245, 1302, 1305, 2421, 2423, 2424, 2425, 2426, 2427, 2428, 2429, 2430, 2432, 2436, 2438, 2439, 2441, 2442
Buck Creek - Bacteria TMDL Report Preparation 8/31/2010 Andrew Sullivan 0207A
Buck Creek Water Quality Sampling / Assessment Project TSSWCB Report Preparation 9/30/2007 Mitch Conine 0207A
Buffalo & Whiteoak Bayous - Bacteria TMDL Submitted for Approval 8/20/2008 Ron Stein 1013, 1013A, 1013C, 1014, 1014A, 1014B, 1014E, 1014H, 1014K, 1014L, 1014M, 1014N, 1014O, 1017, 1017A, 1017B, 1017D, 1017E
Caddo Lake Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling Michele Blair 0401
Caddo Lake Watershed Protection Plan NPS Planning 8/31/2009 Jennifer Delk 0401, 0402, 0407, 0409
Caddo Lake Watershed Sediment Study CRP Completed 8/31/2006 Jennifer Delk 0402, 0402A, 0407, 0409
Camp Meeting Creek - DO TMDL Completed Andrew Sullivan 1806A
Caney Creek UAA WQS Submitted for Approval 4/1/2007 Lori Hamilton 1305
Carters Creek - Bacteria TMDL In Progress 4/22/2009 Ward Ling 1209C
Cedar Creek Reservoir Watershed Protection Plan Implementation NPS In Progress 8/31/2010 Bill Carter 0818
Cedar Lakes - Bacteria (BST) TMDL Report Preparation 8/31/2008 Arthur Talley 2442
Choke Canyon Saltwater Minimization Project NPS Report Preparation 8/31/2009 Anju Chalise 2116
Clear Creek - Chlordane - Fish Tissue Sampling TMDL Completed 8/31/2007 Dania Grundmann 1101, 1102
Clear Creek - Dissolved Solids TMDL Completed 4/12/2006 Andrew Sullivan 1102
Clear Creek - Dissolved Solids - Implementation Plan TMDL Completed Andrew Sullivan 1102
Clear Creek - VOCs TMDL Completed Roger Miranda 1101, 1102
Clear Creek - VOCs - Fish Tissue Sampling TMDL Completed 8/31/2007 Dania Grundmann 1101, 1102
Clear Creek - VOCs - Implementation Plan TMDL Completed Roger Miranda 1101, 1102
Clear Creek Above Tidal Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 8/1/2009 Christine Kolbe 1102
Clear Creek -Chlordane TMDL Completed Roger Miranda 1101, 1102
Clear Creek -Chlordane - Implementation Plan TMDL Completed Roger Miranda 1101, 1102
Clear Creek Watershed - Bacteria TMDL Submitted for Approval 8/20/2008 Ron Stein 1101, 1101B, 1101D, 1102, 1102A, 1102B, 1102C, 1102D, 1102E
Clear Fork Trinity - DO TMDL Completed 5/15/2002 Dania Grundmann 0831, 0833
Composted Manure Incentives NPS Completed 3/31/2006 Bill Carter multi
Construction of Wetland Treatment Systems in the Arroyo Colorado Watershed NPS Planning 8/31/2008 Lauren Bilbe 2201, 2202
Continuous Water Quality Monitoring on Onion Creek NPS Planning 8/31/2009 Mark Palmie 1427
Control of NPS pollution in Hickory Creek NPS Planning 8/31/2008 Mark Palmie 0823
Copano Bay - Bacteria TMDL In Progress 12/14/2009 Ward Ling 2001, 2003, 2472
Cotton Bayou UAA WQS Sampling 9/1/2009 Robert Burgess 2422C
CottonBayou and West Fork Double Bayou Special Study CRP Report Preparation 7/15/2008 Patricia Wise 2422
Cottonwood Branch & Grapevine Creek - Bacteria TMDL Sampling 5/10/2010 Dania Grundmann 0822A, 0822B
Creekside Conservation Program Project TSSWCB In Progress 8/31/2008 Pamela Casebolt 1403
Criteria Evaluation WQS Report Preparation 8/31/2008 Gregg Easley 0105, 0608, 1227, 1238, 1240, 2116
CWQMN/BMP in Salado Creek Watershed NPS In Progress 8/31/2009 Mark Palmie 1910
Cypress Creek Strategic Planning Project NPS Planning 8/31/2010 Allison Woodall 1815
Dallas & Tarrant Co. - Fish Tissue Sampling TMDL Completed 8/31/2008 Dania Grundmann 0805, 0841
Dallas & Tarrant Counties - Legacy Pollutants TMDL Completed Roger Miranda 0805, 0841, 0841A
Dallas & Tarrant Counties - Legacy Pollutants - Implementation Plan SWQM Completed Roger Miranda 0805, 0841, 0841A
Design and Construction of Wetland Treatment System for the City of La Feria NPS Planning 8/31/2009 Anju Chalise 2201, 2202
Development of a Watershed Protection Plan for the Concho River Basin TSSWCB In Progress 7/29/2008 Loren Henley 1421, 1425, 1433
Development of the Plum Creek Watershed Protection Plan TSSWCB In Progress 8/31/2008 Pamela Casebolt 1810
Devils River Continuous Water Quality Monitoring (CWQM) Project SWQM Sampling 8/31/2010 Christine Kolbe 2309
Dickinson Bayou - DO TMDL Submitted for Approval 8/20/2008 Roger Miranda 1103
Dickinson Bayou Nonpoint Source Water Quality Implementation NPS Planning 8/31/2010 Anju Chalise 1103
Dickinson Bayou Tidal Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 8/31/2009 Christine Kolbe 1103
Dickinson Bayou Watershed - Bacteria TMDL In Progress 5/9/2011 Roger Miranda 1103, 1103A, 1103B, 1103C, 1103D, 1104
Dissolve Oxygen Concentration in the headwater of Lake Austin NPS Completed 11/30/2006 Anju Chalise 1403
Diurnal Dissolved Oxygen (DO) Dynamics in Selected Least Disturbed Streams. SWQM Sampling 10/15/2007 Bill Harrison 0402, 0604, 0804, 0823, 1217, 1403, 1414, 1415, 1424, 2107, 2111, 2310, 2453
E.V. Spence Reservoir - TDS TMDL Completed Ward Ling 1411
E.V. Spence Reservoir - TDS - Implementation Plan TMDL Completed Ward Ling 1411
Eastern Houston - Bacteria TMDL Report Preparation 8/17/2009 Ron Stein 1006F, 1006H, 1007F, 1007G, 1007H, 1007I, 1007K, 1007M, 1007O, 1007R
Education of Best Management Practices in the Arroyo Colorado Watershed TSSWCB In Progress 8/31/2008 Pamela Casebolt 2201
Education Program for Improved Water Quality in Copano Bay TSSWCB In Progress 9/30/2009 Mitch Conine 2472
Ellison Creek Reservoir Sediment Toxicity Study. SWQM Completed 8/31/2005 Michele Blair 0404A
Ellis-Prairie SWCD Water Quality Project TSSWCB In Progress 8/31/2008 Lee Munz 0836
Elm & Sandies Creek - DO & Bacteria TMDL Sampling 2/17/2010 Andrew Sullivan 1803A, 1803B
Env. Mon. and Response System (EMRS) Pilot Expansion (Phase II) in the Upper North Bosque Watershed. NPS Sampling 8/31/2008 Anju Chalise 1226, 1226A, 1255
Envirocast Phase II TSSWCB In Progress 4/30/2008 Loren Henley 0805, 0806, 0807, 0810, 0812, 0814, 0820C
Envirocast®: Increasing Nonpoint Source Pollution Prevention Through Watershed Awareness in the Upper Trinity River Watershed TSSWCB Completed 9/1/2007 TJ Helton 0805, 0806, 0810, 0812, 0814, 0820C, 0823A
Extending TMDL Efforts in the North Bosque River Watershed TSSWCB Report Preparation 3/30/2008 Loren Henley 1255
Fate and Transport of E. coli in Rural Texas Landscapes and Streams TSSWCB Report Preparation 9/30/2010 Pamela Casebolt 1209G, 1221A
Fort Worth - Legacy - Fish Tissue Sampling TMDL Completed 8/31/2007 Dania Grundmann 0806A, 0806B, 0829A
Fort Worth - Legacy Pollutants TMDL Completed Roger Miranda 0806, 0806A, 0806B, 0829, 0829A
Fort Worth - Legacy Pollutants - Implementation Plan TMDL Completed Roger Miranda 0806, 0806A, 0806B, 0829, 0829A
Galloway Hammonds Stormwater BMP Demo NPS Completed 8/31/2006 Sherri Serna 1404
Gilleland Creek - - Implementation Plan TMDL Report Preparation 5/25/2009 Ward Ling 1428C
Gilleland Creek - Bacteria TMDL Submitted to EPA for Approval 8/8/2007 Ward Ling 1428C
Greens Bayou - Bacteria TMDL Report Preparation 3/30/2009 Ron Stein 1016, 1016A, 1016B, 1016C, 1016D
Guadalupe Above Canyon - Bacteria TMDL Completed 7/25/2007 Kerry Niemann 1806
Guadalupe Above Canyon - Bacteria TMDL Report Preparation 2/15/2010 Kerry Niemann 1806
Halls Bayou - Bacteria TMDL Report Preparation 5/11/2009 Ron Stein 1006D, 1006E, 1006I, 1006J
Highland Bayou and Marchand Bayou Special Study CRP Report Preparation 7/15/2008 Patricia Wise 2424A, 2424C
Houston Ship Channel - Dioxin TMDL In Progress 4/21/2009 Larry Koenig 0901, 1001, 1005, 1006, 1007, 2421, 2426, 2427, 2428, 2429, 2430, 2436, 2438
Houston Ship Channel - Nickel TMDL Completed Larry Koenig 1001, 1005, 1006, 1007, 1013, 1014, 1016, 1017, 2426, 2427, 2428, 2429, 2430, 2436
Houston Ship Channel - Nickel - Implementation Plan TMDL Completed Larry Koenig 1001, 1005, 1006, 1007, 1013, 1014, 1016, 1017, 2426, 2427, 2428, 2429, 2430, 2436
Houston Ship Channel & Bays - PCBs in Tissue TMDL Sampling 7/14/2010 Larry Koenig 1001, 1005, 1006, 1007, 2421, 2426, 2427, 2428, 2429, 2430, 2436, 2438
Identify and Characterize NPS Bacteria Pollution to Support Implementation of Bacteria TMDLs in the Oso Bay Watershed TSSWCB Report Preparation 9/30/2010 Mitch Conine 2485A
Implementation of the Arroyo Colorado Watershed Protection Plan NPS In Progress 8/31/2008 Jennifer Buratti 2201, 2202
Implementation Support Project in the in Richland-Chambers Reservoir Watershed within the Navarro Soil and Water Conservation District TSSWCB In Progress 8/31/2008 Lee Munz 0836
Implementation Support Project in the Sam Rayburn Reservoir and Toledo Bend Reservoir Watersheds NPS Completed 8/31/2007 Lee Munz 0504, 0610
Lake Austin - DO TMDL Completed Arthur Talley 1403
Lake Austin - DO - Implementation Plan TMDL Completed Arthur Talley 1403
Lake Austin Continuous Water Quality Monitoring (CWQM) Project. SWQM Completed 10/31/2007 Michele Blair 1403
Lake Granbury Continuous Water Quality Monitoring (CWQM) Project SWQM Sampling Jill Csekitz 1205
Lake Granbury Watershed Protection Plan NPS Sampling 8/31/2009 Allison Woodall 1205
Lake Granger Watershed Assessment and Implementation Project TSSWCB In Progress 8/31/2008 Lee Munz 1247A, 1248
Lake Houston - Bacteria TMDL Sampling 11/4/2009 Casey Johnson 1002, 1003, 1004, 1004D, 1004E, 1008, 1008B, 1008H, 1009, 1009C, 1009D, 1009E, 1010, 1011
Lake Mexia UAA WQS Submitted for Approval 12/1/2006 Gregg Easley 1210
Lake O' the Pines - DO TMDL Completed 3/23/2006 Arthur Talley 0403
Lake O' the Pines - DO - Implementation Plan TMDL Submitted for Approval 7/17/2008 Arthur Talley 0403
Lake Palestine Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling Pat Bohannon 0605
Lake Palestine Diurnal Survey SWQM Completed 9/1/2007 Shawna Simpson 0605
Lake Whitney Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 7/31/2008 Pat Bohannon 1203
Lake Whitney Golden Algae Monitoring Project. SWQM Completed 1/1/2006 Christine Kolbe 1203
Lake Worth - PCBs TMDL Completed Roger Miranda 0807
Lake Worth - PCBs - Implementation Plan TMDL Completed Roger Miranda 0807
Lampasas River Watershed Assessment and Protection Project TSSWCB Planning 9/30/2010 Pamela Casebolt 1217, 1217A
Lavaca Bay - Mercury and DO TMDL Completed Faith Hambleton 2453
Lavaca River UAA WQS Report Preparation 5/1/2007 Gregg Easley 1602
LCRA Soil and Water Stewardship Program TSSWCB In Progress 9/30/2010 Pamela Casebolt 1402, 1404, 1405, 1406, 1407, 1408, 1409, 1414, 1415, 1416, 1416A, 1427, 1428, 1428C, 1434
Leon River - Bacteria TMDL Submitted for Approval 8/6/2008 Kerry Niemann 1221
Leon River Watershed Protection Plan Project TSSWCB In Progress 9/30/2009 Pamela Casebolt 1221
Leon San Antonio PCBs TMDL In Progress 12/16/2009 Kerry Neimann 1906
Little River Atrazine Project SWQM Completed 8/10/2004 Brenda Archer 1213
Little Wichita River UAA WQS Report Preparation 5/1/2007 Gregg Easley 0211
LONE STAR HEALTHY STREAMS TSSWCB In Progress 9/30/2009 Mitch Conine 1221, 1810, 1901, 2472
Lower Leon - DO & Bacteria TMDL In Progress 3/19/2012 Kerry Niemann 1906
Lower Pecos River Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 8/31/2010 Christine Kolbe 2310, 2310A, 2311
Lower Rio Grande Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 8/31/2009 Christine Kolbe 2302
Lower Sabine Basin Tidal Study CRP Completed 8/31/2007 Eric Reese 0501
Lower San Antonio River - Bacteria TMDL Submitted for Approval 8/6/2008 Kerry Niemann 1901
Maintaining Sediment Prevention through Repair of Floodwater-Retarding Structures in McCulloch Co. TSSWCB In Progress 3/31/2008 Lee Munz 1416A
Martin Creek Reservoir - Selenium in Fish TMDL Completed Dania Grundmann 0505F
Matagorda/Tres Palacios - DO TMDL Completed 4/30/2007 Roger Miranda 2451, 2452, 2456, 2483A
Mathematical Model for Dispersal of Leaf Beetle, Diorhabda Elongata from Old World released in US for Biological Control of Invasive Saltcedar TSSWCB In Progress 8/31/2008 Pamela Casebolt 1411, 1412
Mid Cibolo Creek - DO TMDL Completed 6/25/2008 Andrew Sullivan 1913
Middle Brazos River Basin - DO TMDL Completed Arthur Talley 1217A
Middle Texas Coast - Oyster Waters Bacteria TMDL In Progress 8/31/2009 Atrhur Talley 1401, 1501, 2441, 2442, 2451, 2452, 2453, 2454, 2456, 2462
Modeling Nutrient Loads from Poultry Operations in the Toledo Bend & Sam Rayburn Reservoir Watershed TSSWCB Completed 3/31/2008 Pamela Casebolt 0504, 0610
Monitoring and Education Programs Focused on Escherichia coli Bacteria and Nutrient Runoff on Dairy Operations in the Leon Watershed TSSWCB Report Preparation 9/30/2009 Pamela Casebolt 1221
Mustang Bayou Systematic Monitoring CRP Completed 8/31/2006 Patricia Wise 2432
Nolan Creek Wasteload Evaluation (WLE) (Segments 1218 and 1219) WQS Report Preparation 12/31/2006 Karen Holligan 1218, 1219
Nolan Creek/South Nolan River - Bacteria TMDL Planning 5/5/2010 Ward Ling 1218
North Bosque II - Remodeling & Sampling TMDL In Progress 10/31/2008 Larry Koenig 1226, 1255
North Bosque River - Phosphorus TMDL Completed Larry Koenig 1226, 1255
North Bosque River - Phosphorus - Implementation Plan TMDL Completed Larry Koenig 1226, 1255
North Bosque River Effectiveness Monitoring NPS Sampling 8/31/2008 Allison Woodall 1225, 1226, 1255
North Concho River Urban NPS Water Pollution Abatement Program; Implementation Project NPS Completed 8/31/2006 Carol Whittington 1421
North Texas Municipal Water District East Fork Monitoring Program CRP Sampling 8/31/2009 Jennifer Delk 0819
Nueces Basin Headwaters Stewardship Project TSSWCB Completed 2/28/2008 Pamela Casebolt 2110, 2113
Nueces Bay - Zinc in oysters TMDL Completed 11/1/2006 Andrew Sullivan 2482
Nueces Bay - Zinc in oysters - Implementation Plan TMDL Completed 10/24/2007 Andrew Sullivan 2482
Nutrient Monitoring on Grapevine Lake CRP Sampling 8/31/2009 Jennifer Delk 0826
Orange County - Bacteria, DO, and pH TMDL Completed 6/13/2007 Ward Ling 0508, 0508A, 0508B, 0508C, 0511, 0511A, 0511B, 0511C, 0511E
Orange County - Bacteria, DO, and pH - Implementation Plan TMDL Report Preparation 12/14/2009 Ward Ling 0508, 0508A, 0508B, 0508C, 0511, 0511A, 0511B, 0511C, 0511E
Oso Bay - Bacteria TMDL Submitted to EPA for Approval 8/22/2007 Larry Koenig 2485
Oso Bay - DO TMDL Completed 3/25/2006 Jason Leifester 2485, 2491
Oso Creek - Bacteria TMDL In Progress 4/11/2011 Larry Koenig 2485A
Oso Creek/Oso Bay Watershed Implementation Assistance TSSWCB Report Preparation 3/31/2008 Lee Munz 2485
Oyster Creek Above Tidal & Atascosa River - DO TMDL Planning 4/16/2013 Ron Stein 1110, 2107
Patrick Bayou 3rd Party - Toxicity TMDL Completed Larry Koenig 1006A
Peach Creek - Bacteria TMDL Submitted for Approval 8/6/2008 Kerry Niemann 1803C
Peach Creek Water Quality Improvement Project TSSWCB In Progress 8/31/2008 Lee Munz 1803C
Pecos River Biological and Habitat survey CRP Completed 8/31/2007 Cory Horan 2311
Petronila Creek - Sulfate, Chloride, TDS TMDL Completed 1/10/2007 Kerry Niemann 2204
Petronila Creek - Sulfate, Chloride, TDS - Implementation Plan TMDL Completed 10/10/2007 Kerry Niemann 2204
Petronila Creek / Oso Bay Public Education & Cleanup Project NPS Planning 8/31/2008 Lauren Bilbe 2203, 2204, 2482, 2484, 2485, 2485A
Petronila Creek Phase II Saltwater Minimization NPS Report Preparation 8/31/2008 Anju Chalise 2204
Petronilla Creek Continuous Water Quality Monitoring (CWQM) Project. SWQM Planning 6/16/2010 Anne Rogers 2204
Phytoremdiation of Excessively High Phosphorus Soils and Subsequent Reduced Phosphorus Runoff into the North Bosque River TSSWCB In Progress 8/31/2008 Loren Henley 1226, 1255
Pine Island Bayou Continuous Water Quality Monitoring (CWQM) Project. SWQM Planning Shawna Simpson 0607
Pine Island Bayou Use Attainability Analysis (UAA) Project. WQS Sampling 10/15/2007 Gregg Easley 0607
PLAN FOR TOMORROW: POULTRY LITTER APPLICATION ON NEW SITES TSSWCB In Progress 8/31/2008 Pamela Casebolt 1242
Possum Kingdom Reservoir (Segment 1207) Continuous Water Quality Monitoring Project. SWQM Sampling 3/31/2009 Pat Bohannon 1207
Produced Water Impacts to Surface Water in the Nueces-Rio Grande Coastal Basin (Petronila Creek) NPS Sampling 8/31/2009 Jennifer Delk 2204
Produced Water Impacts to Surface Water in the Upper Colorado River Basin Downstream of the E. V. Spence Reservoir NPS Sampling 8/31/2008 Jennifer Delk 1426
Produced Water Impacts to Surface Water Quality in the Upper Colorado Basin Upstream of EV Spence. NPS Sampling 8/31/2008 Jennifer Delk 1411, 1426
Reservoir Research TMDL Report Preparation 5/1/2008 Larry Koenig 0818, 0823, 1012, 1216, 1254, 1408, 1604, 1805
Rio Grande - Bacteria TMDL Planning 12/15/2009 Roger Miranda 2302, 2304, 2306, 2307, 2314
Rio Grande Dissolved Minerals Evaluation Project WQS In Progress Gregg Easley 2307
Routine Monitoring of Triazine Herbicides in Navarro Mills Lake (Segment 0817) SWQM Completed 9/15/2004 Brenda Archer 0817
Runnels County Saltwater Minimization NPS Completed 8/31/2006 Sherri Serna 1426
Sabinal River - Nitrate-Nitrite TMDL Completed Ward Ling 2110
Sabinal River - Nitrate-Nitrite - Implementation Plan TMDL Completed Ward Ling 2110
Salado Creek - DO TMDL Completed Arthur Talley 1910
Salado Creek UAA WQS Submitted to EPA for Approval 12/31/2006 Gregg Easley 1910
Sam Rayburn Reservoir Continuous Water Quality Monitoring (CWQM) Project SWQM Planning Steven Earnest 0610
Seven Lakes Atrazine Project SWQM Completed 8/31/2003 Brenda Smith 0303A, 0507, 0815, 0816, 0821, 0836, 0838
Sims Bayou - Bacteria TMDL Report Preparation 3/23/2009 Ron Stein 1007D, 1007N, 1007Q
Slaughter Creek UAA WQS Submitted for Approval 2/28/2005 Gregg Easley 1427A
South Central Texas - Bacteria and DO TMDL Completed Andrew Sullivan 1427, 1906, 1908, 2104, 2107, 2113
Spring Creek UAA WQS Report Preparation 12/31/2008 Gregg Easley 1008
Statewide Ambient Toxicity TMDL Completed Andrew Sullivan 0702A, 1007A, 1209A, 1209B, 2201, 2304, 2306
Statewide Fish Tissue Monitoring Program Tier 1 SWQM Completed 8/1/2007 Pat Bohannon 0199A, 0202, 0203, 0208, 0212, 0213, 0214, 0217, 0223, 0228, 0303, 0303A, 0403, 0405, 0409D, 0502, 0505, 0506, 0506H, 0514, 0515, 0604, 0605, 0610, 0611, 0802, 0804, 0809, 0811, 0812, 0814, 0816, 0817, 0818, 0820, 0823, 0828, 1004, 1006, 1206, 1207, 1208A, 1209I, 1212, 1216, 1221, 1222, 1224, 1225, 1231, 1232, 1233, 1234, 1235, 1240, 1241B, 1247, 1252, 1253A, 1254, 1256, 1403, 1405, 1407, 1412, 1418, 1420, 1421, 1422, 1423, 1426A, 1428, 1433, 1434C, 1804, 1805, 1806, 1807, 1808, 1901, 1911, 2106, 2112, 2116, 2304
Statewide fish Tissue Monitoring Project Tier 2 SWQM Sampling 8/1/2008 Pat Bohannon 0199A, 0212, 0213, 0214, 0404A, 0604, 0815, 1206, 1225, 1241B, 1247, 1433, 1804, 1805
Statewide Polycyclic Aromatic Hydrocarbon (PAH) Survey. SWQM Completed 8/31/2004 Robin Cypher 0102, 0209, 0229, 0303, 0509, 0608, 0815, 1012, 1113, 1203, 1210, 1212, 1222, 1234, 1242, 1415, 1418, 1502, 1805, 1809, 1811, 1812, 1814, 1905, 2113, 2306, 2311, 2451, 2471, 2481, 2491, 2501
Study of Dissolved Oxygen Concentration in Transition Zones of Grapevine Lake, Lewisville Lake and Ray Roberts Lake CRP Sampling 8/31/2009 Jennifer Delk 0823, 0826
Supplemental Funding for the Little River Atrazine Remediation Project TSSWCB In Progress 4/30/2008 Lee Munz 0507, 0836, 1254
Surface Water Quality Monitoring for the Copano Bay Total Maximum Daily Load TSSWCB Sampling 9/30/2009 Mitch Conine 2001, 2003, 2472
Surface Water Quality Monitoring for the Plum Creek Water Protection Plan TSSWCB Sampling 10/31/2008 Pamela Casebolt 1810
SWAT Model Simulation of the Arroyo Colorado Watershed TSSWCB In Progress 3/1/2009 Pamela Casebolt 2201, 2202
Targeted Brush Control in the E.V. Spence Reservoir Watershed TSSWCB Report Preparation 3/31/2008 TJ Helton 1411
Taylor Bayou Above Tidal & Hildebrandt Bayou - DO TMDL Planning 4/16/2013 Ron Stein 0701, 0704
Technical Assistance and Implementation in West Fork of the Trinity River Watershed TSSWCB Report Preparation 8/31/2007 Lee Munz 0812
Technical Assistance Supporting Cooperative Conservation in South Central Texas TSSWCB In Progress 9/30/2009 Lee Munz 1803A, 1803B, 1901, 2107
Texas Coastal Assessment SWQM Sampling 8/31/2008 Christine Kolbe 2412, 2442, 2451, 2452, 2453, 2454, 2456, 2461, 2462, 2471, 2472, 2481, 2482, 2483, 2491, 2492
The Impact of Proper Organic Fertilizer Management in Production of Agriculture TSSWCB In Progress 8/31/2008 Pamela Casebolt 1221, 1221A, 1222
Tidal Streams Use Assessment TMDL Completed 8/23/2007 Jason Leifester 0511, 1501, 2453A
Tidal Streams Use Assessment - Mission and Aransas TMDL Sampling Jason Leifester 2001, 2003
Tier 2 Mercury in East Texas Water Bodies Project. SWQM Sampling 8/1/2008 Pat Bohannon 0204B, 0504, 0505, 0604, 0608, 0611, 0803, 0804, 1003
Tradinghouse Creek Reservoir Metals in Fish Tissue Project. SWQM Completed 9/1/2006 Jill Csekitz 1242
Tres Palacios illegal dumping education and outreach NPS Completed 8/31/2007 Mark Palmie 1401, 1402, 1434
Trinity River - Bacteria TMDL Report Preparation 4/20/2009 Dania Grundmann 0805, 0806, 0822, 0841
Trinity River - PCBs in Tissue TMDL Sampling 2/14/2011 Dania Grundmann 0805, 0806, 0829, 0841
Twenty-four hour Dissolved Oxygen and Use Attainment Initiative SWQM Completed 4/1/2006 Brenda Archer 0306, 0401A, 0402, 0402A, 0409, 0502, 0502A, 0505, 0505B, 0505G, 0507A, 0607A, 0608A, 0608C, 0701, 0704, 0821, 1013A, 1014M, 1016D, 1110, 1202, 1209I, 1211, 1242D
Upper Colorado Phase II Saltwater Minimization NPS Completed 8/31/2006 Sherri Serna 1411
Upper Colorado River Below E.V. Spence - Chloride, TDS TMDL Completed 2/7/2006 Kerry Niemann 1426
Upper Colorado River Below E.V. Spence - Chloride, TDS - Implementation Plan TMDL Completed 10/10/2007 Kerry Niemann 1426
Upper Colorado Saltcedar Control Project: Biological Control Component TSSWCB Report Preparation 3/31/2008 Pamela Casebolt 1411, 1412
Upper Oyster Creek - Bacteria TMDL Report Preparation 4/26/2010 Jason Leifester 1245
Upper Oyster Creek - Bacteria TMDL Completed 8/8/2007 Jason Leifester 1245
Upper Oyster Creek - DO TMDL Report Preparation 7/9/2008 Jason Leifester 1245
Upper Pecos River Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 9/1/2010 Christine Kolbe 2311
Upper Rio Grande Biological Sampling (ALM) SWQM Sampling 8/31/2010 Christine Kolbe 2306
Upper Rio Grande Continuous Water Quality Monitoring (CWQM) Project, Part 2. SWQM Sampling 8/31/2009 Christine Kolbe 2306, 2307
Upper Rio Grande Continuous Water Quality Monitoring (CWQM) Project. SWQM Sampling 8/31/2009 Christine Kolbe 2307
Upper San Antonio River - Bacteria TMDL Completed 7/25/2007 Kerry Niemann 1910, 1910A, 1911
Upper San Antonio River - Bacteria TMDL Report Preparation 10/27/2009 Kerry Niemann 1910, 1910A, 1911
Upper San Antonio WPP NPS Completed 8/31/2007 Bill Carter 1911
Upper Texas Coast - Oyster Water Bacteria TMDL Submitted for Approval 8/8/2008 Ron Stein 2421, 2422, 2423, 2424, 2432, 2439
UT Compost BMP Quarry Trials NPS Sampling 8/31/2008 Bill Carter multi
Watershed Protection Plan Development for Buck Creek TSSWCB In Progress 9/30/2009 Mitch Conine 0207A
Watershed Protection Plan Development for the Pecos River TSSWCB In Progress 8/31/2008 Mitch Conine 2310, 2311
Welsh Reservoir - Selenium in Fish TMDL Completed Dania Grundmann 0404D
West Fork Double Bayou Special Study CRP Completed